| FTMS | Kitchen | 1/17/02 | Floor by 3rd bay sink needs repair, cover hole in wall were pipes go through, remove & replace gasket on freezer door. | Approved | Summer |
| FTMS | 204 | 4/10/02 | Glue molding piece on outside of door. | Approved | 6/30/02 |
| FTMS | 167 | 5/30/02 | Finish installing cable in classrooms. | Approved | 6/30/02 |
| FTMS | Kitchen | 5/31/02 | Repair broken proof box. | Approved | 6/30/02 |
| SBHS | Boys locker room | 11/28/01 | Light shade broken. | Approved | Summer |
| SBHS | 206 | 12/6/01 | Wall in bathroom needs to be patched & painted. | Approved | Summer |
| SBHS | 237 | 1/8/02 | Shade is missing. | Approved | Summer |
| SBHS | 236 | 1/8/02 | Shade broken. | Approved | Summer |
| SBHS | Science Rooms | 1/8/02 | Lab table equipment drawers need locks replaced. | Approved | 6/30/02 |
| SBHS | Outside of 233 | 1/11/02 | Security light is not working. | Approved | 6/30/02 |
| SBHS | 231 | 1/15/02 | Hole in wall in small work room. | Approved | Summer |
| SBHS | Small Elevator | 1/15/02 | Light inside not working. | Approved | 6/30/02 |
| SBHS | 224/225 | 2/12/02 | Remove non-functioning window AC units. Replace with glass. | Approved | Summer |
| SBHS | Girls Track Locker Room | 3/14/02 | Attach girls to door of locker room. | Approved | 6/17/02 |
| SBHS | Library | 4/9/02 | Recover table with new laminate. | Approved | Summer |
| SBHS | Auditorium | 4/10/02 | Lights out in ceiling. | Approved | Summer |
| SBHS | Auditorium | 5/19/02 | 2 ballasts are burned on stage. | Approved | 6/30/02 |
| SBHS | Outside | 5/21/02 | Place posts for east walkway for HS & MS, prep & re-seed lawn. | Approved | By June 15 |
| SBHS | Band Room | 5/22/02 | Emergency light is out. | Approved | 6/30/02 |
| SBHS | Penthouse | 5/30/02 | Correct piping, not working properly. | Approved | 6/30/02 |
| SBHS | Nurse's Bathroom | 6/4/02 | Toilet vibrates when flushed. | Approved | 6/11/02 |
| SBHS | Enrichment Center | 6/11/02 | Install changing table in handicapped bathroom. | Approved | 8/29/02 |
| SBHS | Art Hallway Up | 6/13/02 | The handle of the gym doors near storage is bent. | Approved | 6/17/02 |
| Chamberlin | Media Center | 4/11/01 | Complete installation of TVs, VCRs & racks for placement on cement block wall in classrooms. | Approved | Summer |
| Chamberlin | Kitchen | 3/11/02 | Pressure release is leaking. | Approved | Summer |
| Chamberlin | Playground | 4/1/02 | Need rake & tractor to rake up bark & stones. Need additional stone. | Approved | Summer |
| Chamberlin | Front Lobby Area | 4/3/02 | Check ctu unit, only one speed works. | Approved | 6/30/02 |
| Chamberlin | 15, 3, Cafeteria | 4/9/02 | Cables pulled in rooms & new outlet. | Approved | 6/30/02 |
| Chamberlin | Cafeteria | 5/13/02 | Replace 2 3-way switches for 1st set of lights. | Approved | 6/30/02 |
| Chamberlin | 16 | 5/29/02 | Put shelf on wall over computers. | Approved | Summer |
| Chamberlin | 21 | 6/6/02 | Look at fan, it's quite loud, to see if something can be done. | Approved | Summer |
| Chamberlin | 6 & 13, Air handler 1 | 6/12/02 | Units not running due to noise & air handler relay clicking on & off. | Approved | Summer |
| Orchard | South End of Building | 9/26/01 | Need estimate of feasibility for installing outside water faucet for attending to gardens @ end of building. | Approved | Summer |
| Orchard | Shed | 12/10/01 | Need power & light in shed. | Approved | Summer |
| Orchard | Kitchen | 12/13/01 | Oven not working properly. | Approved | 6/30/02 |
| Orchard | Outside | 1/11/02 | Need crushed white stone for path between school & playground. | Approved | Summer |
| Orchard | Kitchen | 1/28/02 | Repair/replace floor tiles under dishwasher per health dept. | Approved | 6/30/02 |
| Orchard | Playground | 3/19/02 | Need more wood chips for playground surface. | Approved | 6/30/02 |
| Orchard | Main Office | 3/26/02 | Install power outlet. | Approved | 6/30/02 |
| Orchard | Cafeteria & Gym | 4/19/02 | Install 2 fans & put up lights. | Approved | 6/30/02 |
| Orchard | Boys Bathroom | 5/2/02 | Install strainers. | Approved | 6/30/02 |
| Orchard | Front Entrance | 5/2/02 | Repair/replace closer. | Approved | 6/30/02 |
| Orchard | 29 | 5/3/02 | Repair sink & drain. | Approved | Summer |
| Orchard | Outside | 5/10/02 | Replace trim around soffit. | Approved | Summer |
| Orchard | Girl's Bathroom | 6/10/02 | Parts for the door that's fallen off. | Approved | 6/14/02 |
| Orchard | Outside | 6/10/02 | Ballasts burned on security lights. | Approved | 6/14/02 |
| Central | Library | 6/6/01 | Install blinds in library teaching area. | Approved | 6/30/02 |
| Central | Outside Cafeteria | 3/11/02 | Replace ballasts. | Approved | 6/30/02 |
| Central | Playground | 3/11/02 | Bring in dirt. | Approved | Summer |
| Central | Gym Bathroom | 4/3/02 | Toilet is leaking at handle. | Approved | 6/30/02 |
| Central | Driveway | 4/3/02 | Put something on sides. | Approved | 6/30/02 |
| Central | Playground | 5/29/02 | Pea stone for new structure. | Approved | 6/30/02 |