SBSD Maintenance Work Order Status 

(Updated 7/15/05)

 
Electrocuted - Click image to download.

School

 Contact 

Location

Date 
Submitted

Request

Provider

Status

Anticipated
Date of Completion

District tmanazir@sbschools.net bus garage 11/5/04 replace vinyl siding  maintenance approved 4/29/05
FTMS mfrederick@sbschools.net caf 12/3/04 install expanded serving area maintenance approved 4/16/05 consultation
FTMS bmoses@sbschools.net storage room 11/11/04 construct wall for storage maintenance pending 2006 budget
FTMS dpaul@sbschools.net 267 4/16/04 install VCR bracket approved 4/29/05
FTMS bcoleman@sbschools.net 275 10/8/04 create counter top maintenance pending 2006 budget 
FTMS 140 7/14/04 small bookcase & shelving unit custodian pending 2006 budget
SBHS clapine@sbschools.net 225 3/7/05 attach a blackboard or whiteboard maintenance pending budget code
SBHS moday@sbschools.net gym 2/4/05 check basket height, rising to ceiling maintenance approved 4/18/05
SBHS nlavarnway@sbschools.net CDC 1/10/05 rehang the right door to my storage unit maintenance approved 4/28/05
SBHS jmaley@sbschools.net 105 12/3/04 install bulletin board custodian approved 4/28/05
SBHS mfrederick@sbschools.net caf 1 & 11 12/3/04 renovate serving area maintenance approved 4/26/05 consultation
SBHS mfrederick@sbschools.net hallway 12/3/04 repair broken tiles in Sup's kitchen/doorway custodian approved 4/28/05
SBHS kkimball@sbschools.net 241 11/19/04 sand down and finish table maintenance approved 4/28/05
SBHS jkoegler@sbschools.net kitchen 10/28/04 install awnings maintenance pending consultation

 

SBHS cmcdonald@sbschools.net library 11/4/04 retro fit lights maintenance pending consultation
SBHS pburke@sbschools.net 231 9/10/04 consult re: room expansion pending consultation
SBHS cbelton@sbschool.snet 236/prep room 9/17/04 construct shelves pending budget code & consultation
SBHS 139 5/24/04 build wall to seal Mr. Stowell's Office add windowed door pending Spring 
SBHS building exterior 9/19/03  install system to hang banner approved 4/28/05
Chamberlin cchambers@sbschools.net playground 2/11/05 complete list from playground inspection maintenance approved 4/15/05
Chamberlin dlampman@sbschools.net bathrooms 1/5/05 replace linoleum n nurse's bathroom,staff bathroom, and office bathroom maintenance/contractor pending budget code/consultation
Chamberlin jkoegler@sbschools.net kitchen 12/1/04 repair floor tiles maintenance approved 4/29/05
Chamberlin outside 9/8/04 need two vertical gutters approved 4/28/05
Chamberlin dlampman@sbschools.net 14 9/22/04 move cable tv pending consultation
Chamberlin outside overhang 4/29/04 paint approved 4/28/05
Chamberlin maint. 5/5/04 cut book shelves approved 4/29/05
Chamberlin building 4/30/04 install outside speaker system Gear Sound pending pending
Chamberlin dlampman@sbschools.net Student space 9/17/04 need quote to install shelves schedule review springl
Chamberlin 10 7/21/04 install wood approved 4/28/05
Chamberlin EEE 6/17/04 repair shelving approved 4/29/05
Orchard cchambers@sbschools.net playground 2/11/05 complete playground inspection  maintenance approved 4/15/05
Orchard tmanazir@sbschools.net exterior sign 12/16/04 repair sign maintenance approved in progress
Orchard tmanazir@sbschools.net building 12/16/04 remove benches, install coat hooks in 3 classrooms maintenance pending consultation with Rick Ebel
Orchard jbennett@sbschools.net outside 11/17/04 repair bridge on playground equipment maintenance approved parts on order
Central jobrien@sbschools.net fields 2/7/05 relocate baseball field for new parking maintenance pending approval consultation/budget
Central pkolbenson@sbschools.net 8 11/30/04 reglue carpet maintenance pending 4/22/05
Central pkolbenson@sbschools.net health room 11/30/04 reglue flooring maintenance pending 4/22/05
Central pkolbenson@sbschools.net main office 10/27/04 re-glue carpet maintenance pending 4/24/05
Central outside westside of building 2/11/04 repair grill and bricks approved parts on order

Back to: District Offices,SBSD